ExxonMobil sees potential savings of US$2 billion or more on its planned Haimara gas development offshore Guyana by using the same designs, suppliers and construction arrangements as its recently sanctioned Longtail project.
ExxonMobil Guyana President Alistair Routledge told reporters on November 24 that the company is looking to develop Haimara as a second phase of its offshore gas development in the southeastern Stabroek Block.
The approach would allow ExxonMobil to reuse engineering designs and coordinate procurement and fabrication activities across the two projects, reducing the cost of building Haimara.
Routledge said the company plans to use essentially the same design for Haimara's floating production, storage and offloading (FPSO) vessel as the one being built for Longtail.
“If we can reuse the same drawings, the same materials purchases, the same supply chain, go through the same fabrication yards, then we can see a path with an optimized project management team to be able to squeeze significant savings out of the project execution,” he explained.
He said the potential savings could reach US$2 billion or more, making cost control particularly important for Haimara, where the gas resources are more widely distributed than those being developed under Longtail .
However, realizing those savings will depend on keeping Haimara's development schedule aligned with Longtail.
Routledge said ExxonMobil is targeting a final investment decision for Haimara in 2027 to preserve opportunities to share suppliers, equipment and construction arrangements.
Environmental studies for the project are nearing completion, with public consultations on the findings expected to begin early next year.
Longtail, sanctioned in November 2026 at an estimated cost of US$12.5 billion, is expected to begin production in 2030. It will be the Stabroek Block's first major development focused on natural gas and condensate. Condensate production is expected at up to 220,000 barrels per day, while gas production is targeted at up to 1.5 billion cubic feet per day .
Routledge also disclosed that coordination between the projects could produce savings of up to US$200 million on Longtail itself, although the project is still in the early stages of execution.
ExxonMobil intends for Longtail and Haimara to support Guyana's long-term natural gas development, including potential supplies to industries and other consumers onshore.