Two days without power for Berbice residents amid delays in Gas-to-Energy, grid upgrades

Kemol King · November 22, 2026

Thousands of residents in East Berbice-Corentyne faced an electricity outage for nearly two days, as major investments intended to improve Guyana's power supply continue to face delays.

President Irfaan Ali said after 5 p.m. Saturday that the outage had exceeded 45 hours, describing the situation as wholly unacceptable. Over an hour later, the state electricity provider, Guyana Power & Light Inc. (GPL), said works were completed and restoration had commenced, and subsequently announced measures to fix outages in other parts of the country. Meanwhile, the state’s water utility company, Guyana Water Inc. (GWI), said some communities also faced disruptions in their supply due to power failures.

“I recognize the enormous hardship and disruption this is causing families, businesses and entire communities. I sincerely apologize to all those affected,” Ali said in a Facebook post.

The President said residents deserve a clear explanation of what caused the prolonged shutdown and why restoration has taken so long.

Guyana gov't to spend another US$118 million to help finish delayed Gas-to-Energy project

He promised a thorough review of the circumstances surrounding the failure, GPL's response and measures needed to prevent a recurrence.

GPL traced the outage to an insulation failure in the panel housing the grounding transformer at its Canefield Substation.

The utility initially expected to begin restoring electricity by 1 p.m. on Saturday. However, it subsequently said repairs had been completed but additional testing was required before power could be safely restored. It did not provide a new restoration deadline.

Outages are not new to Guyana. GPL has faced reliability challenges for decades, even as the government undertakes major investments in generation, transmission and distribution infrastructure.

A central component of these investments is the 300-megawatt Gas-to-Energy power plant at Wales, which will use natural gas transported from ExxonMobil-operated offshore fields to generate electricity.

The project was initially expected to deliver power in late 2024 but has experienced repeated delays.

The government is now targeting initial testing of the first gas turbine in December 2026, with approximately 57 megawatts expected to become available to the national grid once the unit is commissioned. The remaining units are expected to follow in 2027.

ExxonMobil to conduct gas use and export study for newly approved Longtail project

The additional generation capacity is intended to address electricity shortages as demand increases across Guyana.

Separately, the government is investing US$422.2 million in transmission lines and substations to strengthen the national grid and improve the reliability of electricity delivery.

Contracts were signed with PowerChina and Kalpataru in April 2025 for works including approximately 155 kilometres of 230-kilovolt transmission lines, 167 kilometres of 69-kilovolt lines, five new substations and upgrades to the Kingston Substation.

The projects were initially expected to be completed one year after the May 2025 contract signing. However, in September 2026, GPL reported that several substations were only about 60% complete, while associated infrastructure works remained underway.

The investments include new transmission connections extending towards Berbice, intended to improve the movement of electricity across the main grid, called the Demerara-Berbice Interconnected System.

The government is also pursuing smart-grid technology and network modernization to improve monitoring, fault detection and the management of electricity distribution.

While the Gas-to-Energy plant is expected to address generation shortages, transmission and distribution upgrades are particularly relevant to equipment failures such as the one affecting Canefield.

SBM Offshore clinches sixth Guyana FPSO deal for Longtail’s record-breaking gas processing vessel

Modernized substations and additional transmission pathways could improve network resilience and reduce the impact of some equipment failures, although the extent to which the planned upgrades would prevent a recurrence at Canefield has not been established.

The government expects significant improvements in electricity reliability as the infrastructure projects are completed.

For residents affected by the latest outage, however, those improvements remain unrealized.

Meanwhile, Guyana faces the possibility of further electricity disruptions during the Christmas season as demand continues to outpace available generation.

Minister of Public Utilities and Aviation Deodat Indar said on November 11 that peak demand had reached approximately 269 megawatts, while GPL's operating generating units could supply about 260 megawatts. He said the government was negotiating to secure an additional 20 megawatts for the Christmas period, but could not confirm when the capacity would become available.