With more than 30 discoveries made offshore Guyana, ExxonMobil has a line of sight for the addition of eight floating production, storage, and offloading (FPSO) vessels by 2027, a goal that is expected to see oil production reach 1.7 million barrels per day (b/d).
All projects will be located in the Stabroek Block, in which ExxonMobil holds a 45% operating stake. Hess (30%) and CNOOC (25%) are its co-venturers.
Liza Phase 1

Field(s): Liza
Resource: 450 million barrels of oil
Development wells: 17
First Oil: December 2019
Oil Production Capacity: 160,000 b/d
FPSO Oil Storage Capacity: 1.6 million barrels
Offloading Frequency: Every 5 – 10 days
Estimated Development Cost: US$3.6 billion
Liza Phase 2

Field(s): Liza
Resource: 600 million barrels of oil
Development wells: 33
First Oil: February 2022
Oil Production Capacity: 250,000 b/d
FPSO Oil Storage Capacity: 2 million barrels
Offloading Frequency: Every 4 days
Estimated Development Cost: US$6 billion
Payara

Field(s): Payara, Pacora
Resource: 600 million barrels of oil
Development wells: 35 – 45
First Oil: November 2023
Oil Production Capacity: 250,000 b/d
FPSO Oil Storage Capacity: 2 million barrels
Offloading Frequency: Every 4 days
Estimated Development Cost: US$9 billion
Yellowtail

Field(s): Yellowtail, Redtail
Resource: 925 million barrels of oil
Development wells: 45 – 55
First Oil: 2025 (Expected)
Oil Production Capacity: 250,000 b/d
FPSO Oil Storage Capacity: 2 million barrels
Offloading Frequency: Every 4 days
Estimated Development Cost: US$10 billion
Uaru

Field(s): Uaru, Mako, Snoek
Resource: 800 million barrels of oil
Development wells: 40 – 76
First Oil: 2026 (Expected)
Oil Production Capacity: 250,000 b/d
FPSO Oil Storage Capacity: 2 million barrels
Offloading Frequency: Every 4 days
Estimated Development Cost: US$12.7 billion
Whiptail

Field(s): Whiptail, Pinktail, Tilapia
Resource: 850 million barrels of oil
Development wells: 33 – 72
First Oil: Late 2027 – Early 2028
Oil Production Capacity: 250,000 b/d
FPSO Oil Storage Capacity: 2 million barrels
Offloading Frequency: Approximately every 3-6 days
Estimated Development Cost: US$12.7 billion
Hammerhead (Seeking approval)

Field(s): Hammerhead
Development wells: 14 – 30
First Oil: 2029
Oil Production Capacity: 150,000 b/d
FPSO Oil Storage Capacity: 1.4 million barrels
Longtail (Announced)

Field(s): Longtail
First Oil: 2030
Oil Production Capacity: 240,000 b/d