A timeline of Exxon’s oil development projects in Guyana

Must Read

OilNOW
OilNOW
OilNOW is an online-based Information and Resource Centre

With more than 30 discoveries made offshore Guyana, ExxonMobil has a clear line of sight for the addition of six floating production, storage, and offloading (FPSO) vessels by 2027, a goal that is expected to see oil production exceeding 1.3 million barrels per day (b/d).

All projects will be located in the Stabroek Block, in which ExxonMobil holds a 45% operating stake. Hess (30%) and CNOOC (25%) are its co-venturers.

Liza Phase 1

The Liza Destiny FPSO

Field(s): Liza

Resource: 450 million barrels of oil

Development wells: 17

First Oil: December 2019

Oil Production Capacity: 163,000 b/d

FPSO Oil Storage Capacity: 1.6 million barrels

Offloading Frequency: Every 5 – 10 days

Estimated Development Cost: US$3.6 billion

Liza Phase 2

The Liza Unity FPSO

Field(s): Liza

Resource: 600 million barrels of oil

Development wells: 33

First Oil: February 2022

Oil Production Capacity: 260,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$6 billion

Payara

The Prosperity FPSO

Field(s): Payara, Pacora

Resource: 600 million barrels of oil

Development wells: 35 – 45

First Oil: November 2023

Oil Production Capacity: 238,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$9 billion

Yellowtail

The hull for the Yellowtail FPSO, to be named ONE GUYANA

Field(s): Yellowtail, Redtail

Resource: 925 million barrels of oil

Development wells: 45 – 55

First Oil: 2025 (Expected)

Oil Production Capacity: 250,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$10 billion

Uaru

MODEC’s M350 – Next Generation new build hull to be utilized for the Uaru project FPSO

Field(s): Uaru, Mako, Snoek

Resource: 800 million barrels of oil

Development wells: 40 – 76

First Oil: 2026 (Expected)

Oil Production Capacity: 250,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$12.7 billion

Whiptail

An SBM Offshore multi-purpose floater hull reserved by ExxonMobil for a future Guyana FPSO

Field(s): Whiptail, Pinktail, Tilapia

Resource: 850 million barrels of oil

Development wells: 33 – 72

First Oil: Late 2027 – Early 2028

Oil Production Capacity: 250,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Approximately every 3-6 days

Estimated Development Cost: US$12.7 billion

- ADVERTISEMENT -
[td_block_social_counter]
spot_img

Partnered Events

Latest News

Guyana may enter long-term oil supply deals if there is market oversupply – VP

Guyana's Vice President, Bharrat Jagdeo, said the government may enter a long-term oil supply deal if there is oversupply...

More Articles Like This