A timeline of Exxon’s oil development projects in Guyana

Must Read

OilNOW
OilNOW
OilNOW is an online-based Information and Resource Centre

With more than 30 discoveries made offshore Guyana, ExxonMobil has a clear line of sight for the addition of six floating production, storage, and offloading (FPSO) vessels by 2027, a goal that is expected to see oil production exceeding 1.3 million barrels per day (b/d).

All projects will be located in the Stabroek Block, in which ExxonMobil holds a 45% operating stake. Hess (30%) and CNOOC (25%) are its co-venturers.

Liza Phase 1

The Liza Destiny FPSO

Field(s): Liza

Resource: 450 million barrels of oil

Development wells: 17

First Oil: December 2019

Oil Production Capacity: 163,000 b/d

FPSO Oil Storage Capacity: 1.6 million barrels

Offloading Frequency: Every 5 – 10 days

Estimated Development Cost: US$3.6 billion

Liza Phase 2

The Liza Unity FPSO

Field(s): Liza

Resource: 600 million barrels of oil

Development wells: 33

First Oil: February 2022

Oil Production Capacity: 260,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$6 billion

Payara

The Prosperity FPSO

Field(s): Payara, Pacora

Resource: 600 million barrels of oil

Development wells: 35 – 45

First Oil: November 2023

Oil Production Capacity: 238,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$9 billion

Yellowtail

The hull for the Yellowtail FPSO, to be named ONE GUYANA

Field(s): Yellowtail, Redtail

Resource: 925 million barrels of oil

Development wells: 45 – 55

First Oil: 2025 (Expected)

Oil Production Capacity: 250,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$10 billion

Uaru

MODEC’s M350 – Next Generation new build hull to be utilized for the Uaru project FPSO

Field(s): Uaru, Mako, Snoek

Resource: 800 million barrels of oil

Development wells: 40 – 76

First Oil: 2026 (Expected)

Oil Production Capacity: 250,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$12.7 billion

Whiptail

An SBM Offshore multi-purpose floater hull reserved by ExxonMobil for a future Guyana FPSO

Field(s): Whiptail, Pinktail, Tilapia

Resource: 850 million barrels of oil

Development wells: 33 – 72

First Oil: Late 2027 – Early 2028

Oil Production Capacity: 250,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Approximately every 3-6 days

Estimated Development Cost: US$12.7 billion

- ADVERTISEMENT -
[td_block_social_counter]
spot_img

Partnered Events

Latest News

SBM Offshore’s community initiatives in Guyana promote sustainability, local economies

SBM Offshore’s role in Guyana goes beyond oil production, as its community engagement projects aim to create long-lasting impacts...

More Articles Like This