CNOOC aiming to start up operations in Q4 at UK’s highest-producing oil field

Must Read

OilNOW
OilNOW
OilNOW is an online-based Information and Resource Centre

(S&P Global Platts) China’s CNOOC International confirmed July 8 it expects to start up production from the delayed Phase II expansion project at Buzzard, the UK’s highest-producing oil field, in the fourth quarter 2021.

In a statement, CNOOC said it had successfully installed the project’s “topside” module on June 23 as it seeks to boost flagging output from the field, which is generally the largest source for the Forties crude blend, a major component of the Platts Dated Brent benchmark.

Phase II had been due on stream in the fourth quarter 2020 but was delayed partly to align work with a shutdown of the Forties pipeline for refurbishment, itself postponed from 2020 to June 2021 due to the pandemic. Buzzard itself was shut down for six weeks starting mid-May.

CNOOC “confirms that the heavy lift of the Buzzard Phase II topside module onto the Buzzard ‘P’ platform was safely completed on 23rd June,” the company said. “The heavy lift took place during a planned turnaround of the Buzzard platform and was completed on time with no HSE incidents.”

“First production… is planned for Q4 2021. Subsea bundle installation, as well as topside and subsea hook-up and commissioning are some of the key scopes to be delivered ahead of first oil.”

Buzzard production is closely watched because crude from the field has an impact on the quality of Forties blend, being heavier and more sulfurous than other components.

In production since 2007, Buzzard output has steadily declined since around 2014, averaging around 92,000 b/d in 2020, although that was probably higher than expected because of maintenance being postponed.

Production averaged 64,000 b/d over the first five months of 2021, according to one of the field partners, Harbour Energy.

Phase II entails adding a new subsea production manifold tied to the existing complex and targets parts of the reservoir not previously addressed.

Industry sources have suggested the project will stabilize rather than dramatically increase production, casting doubt on earlier projections that output could reach as high as 135,000 b/d.

In December 2020 one of the field partners, Chrysaor, which subsequently became Harbour Energy, said Phase II drilling results had been “towards the lower end of expectations.” It forecast the Phase II startup to take place in December 2021.

CNOOC acquired its 43.2% operating stake in Buzzard with its 2013 purchase of Canada’s Nexen. Other partners include Canada’s Suncor, with 29.9%, Harbour with 21.7% and One-Dyas with 5.2%.

In Guyana, CNOOC has a 25% stake in the Stabroek Block where over 9 billion barrels of oil equivalent resources have been found since 2015.

- ADVERTISEMENT -
spot_img

Partnered Events

Latest News

Hess says exploration planned this year for Suriname blocks at Guyana border

Hess Corporation said exploration activities are planned this year for two Suriname blocks in which it holds stakes -...

More Articles Like This